A sustainable culvert on site in Valdemarsvik

In 1960, the Fifalla River, which flows through Valdemarsvik into the Valdemars Bay, was culverted. At the end of the 19th century, Lundbergs Läderfabrik was built over the last part of the river at the outlet, but in 1960 a culvert came into place, up to the factory under Storgatan for which the Swedish Transport Administration is responsible.
 
The culvert consisted of galvanized sheet metal and the life expectancy was 50 years. Now that border had been crossed and a couple of years ago a drainage hole appeared in the town hall's parking lot.

Location
Valdemarsvik, Sweden
Complèment
2021
Type de construction
Bâtiment public

A sustainable culvert with a long service life

In 1960, the Fifalla River, which flows through Valdemarsvik into the Valdemars Bay, was culverted. At the end of the 19th century, Lundbergs Läderfabrik was built over the last part of the river at the outlet, but in 1960 a culvert came into place, up to the factory under Storgatan for which the Swedish Transport Administration is responsible. That culvert consisted of galvanized sheet metal and the life expectancy was 50 years. Now that border had been crossed and a couple of years ago a drainage hole appeared in the town hall's parking lot.
 
The old culvert consisted of two halves (upper and lower part) joined together with a bolt and nut. Now they had to unscrew everything, over 4000 bolts that have been underground for over 60 years!
 
After the previous culvert was installed, many other wires and cables have been installed on top over the years, so it has been a matter of getting the new culvert down under these and Valdemarsvik municipality chose a turnkey solution of Weholite in dimension 1400 mm, for the new culvert stretch below Storgatan and
Uponor Infra's field service personnel, were on site, installed, and welded the pipes together in collaboration with Svevia.
 
With Uponor Infra 360° Project Services and Weholite, the municipality of Valdemarsvik got a safe, durable and easy-to-install plastic pipe solution that lasts for over 100 years.
 
 
Projets similaire

Pump structure secures stormwater system’s long life

Pump structure secures stormwater system's long life in Jyllinge Nordmark

The power supply to the East Helsinki metro network will be protected with Uponor FastGuard

In the fall of 2024, a groundbreaking electrical renovation was carried out on the metro line between Siilitie and Kulosaari in Helsinki. The aim was to improve the metro line's power supply and ensure its functionality during potential faults as part of a broader ring network solution. The project utilized FastGuard cable protection developed by Uponor, which is lightweight, durable, and quick to install.

Uponor Flowise drinking water solution to Levi's tourism mecca

The ski slopes of Levi attract thousands of tourists every year. Water consumption varies greatly, which is why the water intake plant in Kirakka in Levi was renovated to meet the consumption peaks during peak seasons. As part of the project, Uponor delivered two huge reservoir tanks to ensure sufficient supply of clean water in the area.

The power supply to the East Helsinki metro network will be protected with Uponor FastGuard

In the fall of 2024, a groundbreaking electrical renovation was carried out on the metro line between Siilitie and Kulosaari in Helsinki. The aim was to improve the metro line's power supply and ensure its functionality during potential faults as part of a broader ring network solution. The project utilized FastGuard cable protection developed by Uponor, which is lightweight, durable, and quick to install.