ProFuse pressure pipe line provides drinking water to cottage owners in islands near by Uusikaupunki
14 km long ProFuse pressure water line was installed under the sea in Uusikaupunki 2009.
Location
Uusikaupunki, Finland
Valmimisaeg
2010
Hoone tüüp
Municipal
Product systems
Potable water
Projekti tüüp
Uusehitis
Uusikaupunki is known its car manufactory but also its islands. Numerous islands have lots of cottages which inquires some municipal engineering. Earlier drinking water was brought to the islands in canisters when the cottage owners arrived. Nowadays there are water cooperative called Uki-Kustavi that provides water line pipe to the islands’ cottages.
Uki-Kustavi is a water utility company cooperative that was established in 2006. The main project for the cooperative in 2009 was to install a pressure water pipe line from Suukari to Humalkari. The main line is 14 km long and together with all the 170 branches, the length of the pressure water line in total is 66 km.
The most interesting part of the project is that the pressure pipe line is installed into the sea, and even to the bottom of the sea. When working at the sea, the weather is always the key question. It can delay the installation radically.
Kustavin Asentajat Ky won the installation contract. The excavator contractor of the project was Vestiö Oy. The water pressure pipe used in installation was Uponor’s ProFuse pressure pipe for drinking water. The diameter of the pipe is ø 110 mm.
Uki-Kustavi is a water utility company cooperative that was established in 2006. The main project for the cooperative in 2009 was to install a pressure water pipe line from Suukari to Humalkari. The main line is 14 km long and together with all the 170 branches, the length of the pressure water line in total is 66 km.
The most interesting part of the project is that the pressure pipe line is installed into the sea, and even to the bottom of the sea. When working at the sea, the weather is always the key question. It can delay the installation radically.
Kustavin Asentajat Ky won the installation contract. The excavator contractor of the project was Vestiö Oy. The water pressure pipe used in installation was Uponor’s ProFuse pressure pipe for drinking water. The diameter of the pipe is ø 110 mm.